How We Use AI
How we use AI on your project
Calling the company AI-native does not mean handing a construction project over to AI. It means using AI with enough project context and construction experience behind it that the output actually improves how we deliver projects. Our context layer holds the drawings, the specifications, the schedule, the meetings and the open decisions for each project, and it carries the lessons learned from prior project experience. It reads a drawing set and finds the conflicts an experienced builder would look for, turns a week of meetings into prioritized action items, and flags what needs a decision and when. Experienced builders review the output and make the decisions.
On your job
Three things it does on a job today
In the owner meeting
When a design change comes up, the decision is made with the full picture.
We ask the record what the change does to the schedule and which open RFIs and submittals it touches, and the answer is on the table in the meeting, with its sources. The decision gets made while there is still time to act on it.
- For
- Owner
- Design team
Move the bar to the east wall?
- Schedule
- The bar top stone selection drives the millwork install and is needed by 21 November. Moving the bar restarts it.
- Open items it touches
- RFI 142, the ceiling layout, still open. Millwork submittal, held for the stone.
- Needed by
- Friday 23 October, to hold the opening date.
From the schedule update, the RFI log and the submittal logRead out by the project lead
Every week
A Friday briefing for each person on the job.
One for you, one for the design team and one for each trade: what you need to know this week and what we need from you, by when. The project lead reads each one before it goes out.
- For
- Owner
- Design team
- Trades
Any day
Ask a question. The answer comes from your project’s own record.
Owners, consultants and subcontractors can ask where the job stands. Every answer shows its sources, and when the record is silent it says so. Anything that affects a decision, a builder confirms.
- For
- Owner
- Consultants
- Subcontractors
Has the landlord approved the storefront?
Nothing in this job’s records says that. The storefront drawings went to the landlord for review, and no response is logged.
SourceSubmittal log · Meeting notes · Correspondence
From the project record, with sourcesCheck the sources, or ask us
What is behind it
A context layer for the company, and the context for each job
The context layer has two halves. One is how we build: our methods, our checklists and the lessons from prior experience, kept once for the whole company. The other is the active project: the drawings, the specifications, the schedule, the meeting record and the open decisions. The assistant reads both.
This is what makes it more than paying for a tool or giving everyone a license to an LLM. A general AI tool knows nothing about your project or how we build. Our system incorporates context that delivers value to our clients.
What stays with people
Augmentation, not automation
What a person always does is the judgment: pricing, commitments, and anything that is sent to you. Experienced builders review the output against the project information and decide what needs to happen next.
An answer from the system is an interpretation of the record. It is not the record, an approval or a decision. Formal decisions are recorded in the project platform, by a person.
The tools
What we run the company on
- MiloMacDougall Builders’ custom AI agent and context layer
- ConstructableProject management, built to work with AI
- NotionCompany management
- HardlineCalls recorded and transcribed, so phone calls become project context
- ClaudeThe model Milo runs on
- Microsoft ProjectOur scheduling software
Examples
What this looks like in the work
IllustrativeBoth examples run on a sample project: the situation, what the system drafted and what the person decided.
Example 01
The schedule look-ahead
- The situation
- The light fixtures are now due on Tuesday of week 3. The install was planned for Friday of week 2.
- What the system drafted
- The look-ahead with RFI 142 and the late delivery added, the three activities behind the fixtures pushed out, and a hot list of who owns what.
- What the person decided
- The superintendent approved the two additions, held the date changes and asked the electrician to expedite or ship a partial order.
Read from the master schedule, the RFI log and the procurement logEvery date change waits for the superintendent
Example 02
A specialty trade playlist
We keep a playbook for each specialty trade, built with prior experience on similar projects: what went wrong, what to check and when. It travels with the subcontract from the first drawing to closeout, as a guide and a roadmap, so the same mistake does not happen twice.
- 00 Metal framing and drywall playbook.md
- Scope and subcontract.md
- Exclusions to look out for.md
- Durations and lead times.md
- Local jurisdiction code.md
- Industry standards (ASTM, ANSI, UL).md
- Drawing gaps.md
- Change orders.md
- Quality checklist.md
Metal framing and drywall / Drawing gaps.md
Drawing gaps
From prior experience on similar projects
- Architectural and structural drawings disagree
One set shows metal stud framing where the other shows wood, and the two disagree on whether plywood sheathing is required at the wall.
- Shows up
- Bid, or at the framing submittal
- Resolved by
- The architect and the structural engineer
- At bid
- A bid question, priced to the more stringent condition until it is answered
- Wall tags with no wall type
Tags on the floor plan point to partition types that are not in the partition schedule, so the stud gauge, the board layers and the rating are unknown.
- Shows up
- Bid, and again at layout
- Resolved by
- The architect
- At bid
- A bid question, with any unanswered tags qualified
- Partitions not dimensioned from a control line
Walls are dimensioned to each other, or not at all, instead of to a gridline or control line, so the first day of layout turns into field decisions.
- Shows up
- Day one of layout
- Resolved by
- The architect, before layout starts
- At bid
- Checked at bid, with missing dimensions sent as questions before mobilization
One playbook for each specialty tradeUpdated at closeout
- 01Drawings receivedTarget scope gaps typically missed
- 02Scope developedGenerate scope from plans and previous project context
- 03Bid receivedExclusions read against the scope
- 04Contract awardedLead times and lessons written into the subcontract
- 05Submittal and pre-mobilizationPre-mobilization conference for smooth onboarding
- 06Construction and punch listQA/QC managed proactively
- 07CloseoutWhat we learned goes back into the playbook
Questions
AI on your project, asked plainly
Does this replace the people on my job?
No. It gives experienced builders the project context in front of them, so their time goes to the judgment the job needs.
How do you use AI on a project?
Our system reads the drawings, the specifications, the schedule, the meeting notes and our SOPs, alongside the lessons learned from prior project experience. Experienced builders review the output against the project documents and decide what to do with it. Owners, consultants and subcontractors get access to the same system, so they can ask questions of the project record and stay informed on the information that matters to them.
How is this different from using a chatbot?
A chatbot knows nothing about your project or how we build. Ours reads your job’s own records and our written methods before it answers, and says where each answer came from.
Start with a conversation
Let’s talk about your project
Tell us what you are planning, where the design stands and the date you are working toward. We will call to talk it through.