Hospitality construction in Los Angeles

Bars, lounges, clubs and amenity spaces, finished to the operator’s standard and sequenced around guests and staff.

  • A dining room seen through a wide arch, with brass pendant lights, banquettes and trees beyond
    Project completed as General Superintendent at Shawmut Design and ConstructionBuilt by Shawmut Design and Construction. Luke MacDougall, General SuperintendentLuke MacDougall’s project as General Superintendent at Shawmut Design and ConstructionShawmut Design and ConstructionLuke MacDougall, General Superintendent
  • A private lounge with blue felt walls, a terrazzo counter and exposed timber joists
    Project completed as President at Reaume RichardsonBuilt by Reaume Richardson. Luke MacDougall, PresidentLuke MacDougall’s project as President at Reaume RichardsonReaume RichardsonLuke MacDougall, President
  • A long bar with a lit blue velvet front and a backlit drinks menu above the back bar
    Project completed as President at Reaume RichardsonBuilt by Reaume Richardson. Luke MacDougall, PresidentLuke MacDougall’s project as President at Reaume RichardsonReaume RichardsonLuke MacDougall, President

What decides the job

What we plan around on a hospitality project

Most hospitality work happens while the venue stays open, to a standard set by the operator, and is reviewed by the operator’s team as well as the city.

  1. 01

    The building stays open

    Work is sequenced around guests, members and staff, with the noisy work and the shutdowns planned with the operator in advance.

  2. 02

    The operator’s standard

    The operator’s design standard and review steps go on the schedule beside the city’s inspections, so their sign-off never holds up opening.

  3. 03

    The finish is the product

    Guests experience the room through its finishes, so the millwork, stone, lighting and upholstery are chosen and built for durability as much as for looks, with samples and mockups approved early.

Before you start

The pre-mobilization checklist

We believe most of what goes wrong on a construction project can be prevented with detailed planning up front and alignment across the full team. This is the list we work through with an owner before mobilization, so that on the first day of construction we have a clear path forward.

Who provides what

  • Every owner-furnished item is on a delivery log in the schedule, with who buys, receives, stores, installs and connects it, and the date it is needed on site.
  • Furniture, equipment, signage, audiovisual, security and data are each assigned to the owner or the contractor, down to who provides the conduit, the cable and the devices.
  • For each owner-furnished item, the backing, power, conduit and final connection our trades still owe it are assigned and priced.
  • The owner’s own vendors are named, with their insurance, the site rules and the date their in-wall requirements are due before walls close.
  • Utility accounts for power, gas, water and data are open in the right name, and each provider has confirmed its account in writing.

Design and decisions

  • The set issued for construction includes every agreed value engineering change and bid answer, in every discipline.
  • Every finish is tagged to one product, color and finish, and each open selection has a decision date worked back from its lead time.
  • Each allowance names what it stands in for, who answers it and the date it becomes a firm price.
  • The construction plans include layout dimensions for all partitions and relate back to grid lines.
  • A consolidated RCP has been issued, showing the ceiling finishes with all MEP systems overlaid.
  • The owner’s equipment list, with each item’s power, heat and weight, is with the engineers, so the service, the cooling and the structure are sized from it.

Permits and approvals

  • The building permit is issued, and its description names every scope that will be inspected.
  • Whoever controls the building, the landlord or the operator, has approved the drawings and the construction rules in writing.
  • Approvals outside the building department are tracked with the agency, who holds each one and its date: public works, each utility, the fire department and the air quality district.
  • Every deferred submittal, such as fire sprinkler, fire alarm or storefront, has its own plan check time on the schedule.
  • The special inspector has been hired by ownership, and their contact information has been shared with the team.

Procurement

  • Long lead items are identified, and drop-dead dates have been established from each item’s required-on-job date and estimated lead time.
  • Items that wait on an outside approval are logged with that approval as their trigger, such as switchgear, which waits on the utility.
  • The submittal schedule has been reviewed and confirmed with all reviewers, using their real review times, with a resubmission round carried for millwork and steel.
  • The trade partners for the first eight weeks are under contract, and every other trade has a planned award date.

The site

  • Existing conditions, including neighboring properties and shared areas, are photographed and video recorded with dates before work starts.
  • Hours for loud work, quiet work and deliveries are confirmed in writing, with loading, parking and elevator use.
  • A site logistics plan covering deliveries, hoisting and laydown is issued to every trade and named in each subcontract.
  • Every existing utility and meter is confirmed active, and every new service has its application filed and dated back from when it is needed.
  • The site safety plan and the emergency plan are posted, with the muster point identified.
  • Neighbors and other tenants know the schedule and who to call, and the calendars of noise-sensitive neighbors are in hand before demolition.

Financials and reporting

  • The schedule of values for invoicing is established, and the payment calendar has been reviewed and confirmed between ownership and the lender.
  • The weekly owner report has a confirmed format and a scheduled weekly distribution time.
  • Additional insured endorsements are confirmed, and approved insurance certificates are on file.
  • The weekly meeting schedule is set for the owner, the design team and the trades.

For a hospitality space

  • The operator’s blackout dates, event calendar and quiet hours, often tighter than the city’s, are in writing and on the schedule.
  • Shutdowns of power, water, fire alarm and elevators are requested with the notice the building needs, and the fire alarm test window for dusty work is agreed with the building engineer in writing.
  • Mockups are scheduled for the critical details, each with a date and who approves it.
  • Each room passes a pre-punch walk before the owner’s furniture installers are let in, and who protects finished rooms through the opening events is settled.
  • Water shutoffs, pressure tests and drain connections near finished or occupied rooms run under a written wet work permit.
This checklist as a PDFPDF

The PDF of this checklist is on its way. Email hello@macdougallbuilders.com and we will send it when it is ready.

Questions

Hospitality, asked plainly

Can the space stay open during the work?

Often part of it can. We plan the phases with the operator, separate the work from the public, and keep the path guests use clean and safe every day.

When should the operator’s team be involved?

From the start of preconstruction. Their standards, calendar and opening plans shape the budget and the schedule, so we bring them into the first review of the drawings.

How do you protect finished work?

Finished areas are protected and closed to trades as they complete, and the sequence is built so nobody has to work back through a finished room.