What We Build

Creative office construction in Los Angeles

Open ceilings and exposed systems, where every duct and conduit run becomes part of the finish.

  • An office pantry with timber shelving
    Project completed as General Superintendent at Shawmut Design and ConstructionBuilt by Shawmut Design and Construction. Luke MacDougall, General SuperintendentLuke MacDougall’s project as General Superintendent at Shawmut Design and ConstructionShawmut Design and ConstructionLuke MacDougall, General Superintendent
  • A steel and glass office entry with a stair behind it
    Project completed as President at Reaume RichardsonBuilt by Reaume Richardson. Luke MacDougall, PresidentLuke MacDougall’s project as President at Reaume RichardsonReaume RichardsonLuke MacDougall, President
  • A block-walled office space under exposed timber joists, with a glass roll-up door open to a planted yard
    Project completed as President at Reaume RichardsonBuilt by Reaume Richardson. Luke MacDougall, PresidentLuke MacDougall’s project as President at Reaume RichardsonReaume RichardsonLuke MacDougall, President

What decides the job

What we plan around on a creative office

Creative office leaves the building exposed: open ceilings, polished slabs, visible duct and conduit. With nothing to hide it behind, every run of pipe is part of the finish, and so is the coordination between trades.

  1. 01

    Everything shows

    With open ceilings, the route of every duct, pipe and conduit is a design decision, and it is coordinated before anything is installed.

  2. 02

    The slab and the structure

    Polished concrete, exposed steel and timber are finished surfaces, and every penetration, anchor and patch in them is planned so it does not show.

  3. 03

    Sound

    Open space and hard surfaces need the acoustic work planned in, not added after the tenant moves in.

Before you start

The pre-mobilization checklist

We believe most of what goes wrong on a construction project can be prevented with detailed planning up front and alignment across the full team. This is the list we work through with an owner before mobilization, so that on the first day of construction we have a clear path forward.

Who provides what

  • Every owner-furnished item is on a delivery log in the schedule, with who buys, receives, stores, installs and connects it, and the date it is needed on site.
  • Furniture, equipment, signage, audiovisual, security and data are each assigned to the owner or the contractor, down to who provides the conduit, the cable and the devices.
  • For each owner-furnished item, the backing, power, conduit and final connection our trades still owe it are assigned and priced.
  • The owner’s own vendors are named, with their insurance, the site rules and the date their in-wall requirements are due before walls close.
  • Utility accounts for power, gas, water and data are open in the right name, and each provider has confirmed its account in writing.

Design and decisions

  • The set issued for construction includes every agreed value engineering change and bid answer, in every discipline.
  • Every finish is tagged to one product, color and finish, and each open selection has a decision date worked back from its lead time.
  • Each allowance names what it stands in for, who answers it and the date it becomes a firm price.
  • The construction plans include layout dimensions for all partitions and relate back to grid lines.
  • A consolidated RCP has been issued, showing the ceiling finishes with all MEP systems overlaid.
  • The owner’s equipment list, with each item’s power, heat and weight, is with the engineers, so the service, the cooling and the structure are sized from it.

Permits and approvals

  • The building permit is issued, and its description names every scope that will be inspected.
  • Whoever controls the building, the landlord or the operator, has approved the drawings and the construction rules in writing.
  • Approvals outside the building department are tracked with the agency, who holds each one and its date: public works, each utility, the fire department and the air quality district.
  • Every deferred submittal, such as fire sprinkler, fire alarm or storefront, has its own plan check time on the schedule.
  • The special inspector has been hired by ownership, and their contact information has been shared with the team.

Procurement

  • Long lead items are identified, and drop-dead dates have been established from each item’s required-on-job date and estimated lead time.
  • Items that wait on an outside approval are logged with that approval as their trigger, such as switchgear, which waits on the utility.
  • The submittal schedule has been reviewed and confirmed with all reviewers, using their real review times, with a resubmission round carried for millwork and steel.
  • The trade partners for the first eight weeks are under contract, and every other trade has a planned award date.

The site

  • Existing conditions, including neighboring properties and shared areas, are photographed and video recorded with dates before work starts.
  • Hours for loud work, quiet work and deliveries are confirmed in writing, with loading, parking and elevator use.
  • A site logistics plan covering deliveries, hoisting and laydown is issued to every trade and named in each subcontract.
  • Every existing utility and meter is confirmed active, and every new service has its application filed and dated back from when it is needed.
  • The site safety plan and the emergency plan are posted, with the muster point identified.
  • Neighbors and other tenants know the schedule and who to call, and the calendars of noise-sensitive neighbors are in hand before demolition.

Financials and reporting

  • The schedule of values for invoicing is established, and the payment calendar has been reviewed and confirmed between ownership and the lender.
  • The weekly owner report has a confirmed format and a scheduled weekly distribution time.
  • Additional insured endorsements are confirmed, and approved insurance certificates are on file.
  • The weekly meeting schedule is set for the owner, the design team and the trades.

For a creative office

  • Exposed duct, pipe and conduit routes are drawn and reviewed with the design team before installation.
  • The finish standard for exposed work is agreed with a mockup.
  • Lighting, sprinkler heads and diffusers in the open ceiling are laid out together and approved by the design team before rough-in.
  • Acoustic treatment is coordinated in the design and budget.
  • Furniture, power and data locations are confirmed before trenching and coring.
This checklist as a PDFPDF

The PDF of this checklist is on its way. Email hello@macdougallbuilders.com and we will send it when it is ready.

Questions

Creative office, asked plainly

How do you keep exposed work looking intentional?

The trades’ routes are coordinated on paper first, a mockup aligns the standard, and the first area installed is reviewed with the design team before the scope continues.

Can you polish an existing slab?

Usually. We sound the slab for hollow spots, map cracks and any heaving with the finisher, and confirm which cracks can be infilled with epoxy before you commit to a polished finish.

Do you build the base building as well?

Yes. We build ground-up and adaptive reuse projects as well as the finishes of the project.