Sample report · no amounts shown

Weekly owner report

A restaurant in an existing building · Week 15 of 24

Issued Friday

  • 61 daysTo substantial completion
  • 58%Complete, by schedule
  • 2Decisions that are yours
  • 2Items at risk

Decisions and concerns

  • Approve the bar top stoneBy Wednesday, to hold the fabrication slot
  • Approve CO 05, the added floor sinkBy Friday, before the slab is patched
  • Risk: kitchen equipment is one week lateOur recommendation: no action yet. The week is absorbed before the health department final.

Photographs

  • 01 Dining room: ceiling framing complete
  • 02 Kitchen: hood set, duct to roof in progress
  • 03 Bar: plumbing rough-in inspected
  • 04 Restrooms: tile started
  • 05 Storefront: frames delivered
  • 06 Back corridor: held for RFI 041

Narrative and manpower

Ceiling framing finished in the dining room and the kitchen hood was set on Tuesday. The grease duct is two floors from the roof. Plumbing rough-in at the bar passed inspection on Thursday. Tile started in the restrooms a day early. The back corridor is on hold until the ceiling height is answered.

TradeMonTueWedThuFri
Framing and drywall66644
Electrical33444
Plumbing22233
Mechanical33332
Tile00222

Safety

  • 1Audit finding, corrected the same day
  • 16Workers at this week’s safety talk
  • 3New workers oriented

Safety talk: ladder use around the dining room ceiling work. The weekly audit found one damaged extension cord at the bar, removed the same day.

Schedule

  • On track

    Substantial completion is holding at Week 24.

  • 61 days

    To substantial completion

Milestones in the next two weeks

MilestonePlannedForecastStatus
Walls closedWeek 16Week 16On time

RFIs and submittals

ItemSubjectStatusWaiting on
RFI 041Ceiling height at back corridorSchedule at riskArchitect, due Friday
RFI 038Floor drain location at barOverdue 3 daysKitchen designer
Submittal 019Bar top stoneWaiting on youApprove by Wednesday
Submittal 022Pendant lightingIn reviewArchitect, on time
RFI 044Door hardware at storageOpenArchitect, on time

Payment application

  1. SubmittedThe 25th
  2. Architect reviewComplete
  3. Owner reviewWith you since Monday
  4. PaymentDue the 15th

Application 4 is with you for review. Applications 1 to 3 are paid, and nothing is past due.

Open change orders

NumberDescriptionStatus
CO 05Added floor sink at barWaiting on your approval
CO 06Upgraded dining room dimmingBeing priced
CO 07Landlord-required roof curbWith the landlord