Sample report · no amounts shown
Weekly owner report
A restaurant in an existing building · Week 15 of 24
Issued Friday
- 61 daysTo substantial completion
- 58%Complete, by schedule
- 2Decisions that are yours
- 2Items at risk
Decisions and concerns
- Approve the bar top stoneBy Wednesday, to hold the fabrication slot
- Approve CO 05, the added floor sinkBy Friday, before the slab is patched
- Risk: kitchen equipment is one week lateOur recommendation: no action yet. The week is absorbed before the health department final.
Photographs
- 01 Dining room: ceiling framing complete
- 02 Kitchen: hood set, duct to roof in progress
- 03 Bar: plumbing rough-in inspected
- 04 Restrooms: tile started
- 05 Storefront: frames delivered
- 06 Back corridor: held for RFI 041
Narrative and manpower
Ceiling framing finished in the dining room and the kitchen hood was set on Tuesday. The grease duct is two floors from the roof. Plumbing rough-in at the bar passed inspection on Thursday. Tile started in the restrooms a day early. The back corridor is on hold until the ceiling height is answered.
| Trade | Mon | Tue | Wed | Thu | Fri |
|---|---|---|---|---|---|
| Framing and drywall | 6 | 6 | 6 | 4 | 4 |
| Electrical | 3 | 3 | 4 | 4 | 4 |
| Plumbing | 2 | 2 | 2 | 3 | 3 |
| Mechanical | 3 | 3 | 3 | 3 | 2 |
| Tile | 0 | 0 | 2 | 2 | 2 |
Safety
- 1Audit finding, corrected the same day
- 16Workers at this week’s safety talk
- 3New workers oriented
Safety talk: ladder use around the dining room ceiling work. The weekly audit found one damaged extension cord at the bar, removed the same day.
Schedule
- On track
Substantial completion is holding at Week 24.
- 61 days
To substantial completion
Milestones in the next two weeks
| Milestone | Planned | Forecast | Status |
|---|---|---|---|
| Walls closed | Week 16 | Week 16 | On time |
RFIs and submittals
| Item | Subject | Status | Waiting on |
|---|---|---|---|
| RFI 041 | Ceiling height at back corridor | Schedule at risk | Architect, due Friday |
| RFI 038 | Floor drain location at bar | Overdue 3 days | Kitchen designer |
| Submittal 019 | Bar top stone | Waiting on you | Approve by Wednesday |
| Submittal 022 | Pendant lighting | In review | Architect, on time |
| RFI 044 | Door hardware at storage | Open | Architect, on time |
Payment application
- SubmittedThe 25th
- Architect reviewComplete
- Owner reviewWith you since Monday
- PaymentDue the 15th
Application 4 is with you for review. Applications 1 to 3 are paid, and nothing is past due.
Open change orders
| Number | Description | Status |
|---|---|---|
| CO 05 | Added floor sink at bar | Waiting on your approval |
| CO 06 | Upgraded dining room dimming | Being priced |
| CO 07 | Landlord-required roof curb | With the landlord |